Our Projects...

Conveyor Products and Solutions has a proven track record of delivering innovation and sustainable value to customers for their existing operations, as well as greenfield and brownfield expansion projects. The CPS team safely delivered high accuracy, light weight, low-noise, low rolling-resistance idlers for overland conveyors to the Rio Tinto Silvergrass project and the BHP Jimblebar expansion project, exceeding the technical and commercial performance KPIs. CPS has also supplied high quality Australian components internationally to the First Quantum Minerals' Cobre Panama copper project and other mine expansions in Asia and Africa.

You can download an overview of our project experience from the link. 

Recently Completed Projects

FQM Cobre Copper Project – Panama
Silvergrass Project – Pilbara
Jimblebar Project – Pilbara
FQM Cobre Copper Project – Panama


FQM Cobre Copper Project

Owner/Operator: First Quantum Minerals
Date 2018
EPCM: Lycopodium
Rollers: 60000
Idlers: 18000 

Cobre Panama is a large open-pit copper development project in Panama. The concession is located 120km west of Panama City and 20km from the coast of the Caribbean Sea. The project included multiple 600 – 2600mm wide conveyors.

CPS FQM Cobre Copper Site

Silvergrass Project – Pilbara
Silvergrass Project

Owner/Operator: Rio Tinto Iron Ore
Date: 2017
EPCM: RCR Tomlinson
Rollers: 19000
Idlers: 6000

Silvergrass is a satellite deposit located adjacent to Rio Tinto’s Nammuldi mine and is part of the Greater Nammuldi precinct, approximately 70km north-west of Tom Price. The project included multiple 900 – 1800mm wide conveyors with frames of ±0.5mm tolerance after galvanising.

CPS Silvergrass Overland Conveyor

Jimblebar Project – Pilbara
Jimblebar Project

Owner/Operator: BHP Iron Ore
Date: 2016
EPCM: Sedgman Civmec Joint Venture
Rollers: 17000
Idlers: 5400

The Jimblebar iron ore mine is located 40km east of Newman in the Pilbara region of Western Australia. The project included multiple 1600 – 2400mm wide conveyors with frames of ±0.5mm tolerance after galvanising.

CPS Jimblebar Conveyor

Selection of Past Projects

Iron Ore Facility
Queensland Coal
Talison Lithium Project
Iron Ore Facility
Download Case Study

- Product: Polyurethane Disc Rollers
- Material: Iron Ore
- Bulk 10,000 Tonnes Per Hour
-Result: Lower Life Cycle Cost; approximately 30% of the LCC of steel rollers
Queensland Coal
DOWNLOAD Case Study

  • Yeloroll Carry - 3757
  • Impact Idlers - 519
  • PU Returns & Weightometer - 313
  • Total Installation - 4589
Talison Lithium Project
Talison Lithium Project – MSP 2018
  • Multiple conveyors 600 - 1,800mm wide.
  • Idler and pulley package delivered in 20 weeks.


Ok Tedi Mining Crusher Replacement Project
Gruyere Gold Project
Dugald River Project
Ok Tedi Mining Crusher Replacement Project
Ok Tedi Mining Crusher Project – GRES 2019
  • 2,000mm conveyor Idler package
  • Delivered in 14 weeks.



Gruyere Gold Project
Gruyere Gold Project -  Amec Foster Wheeler Civmec JV - 2018
  • Multiple conveyors 600-1800mm wide.
  • Idler package delivered in 16 weeks.


Dugald River Project
Dugald River Project - RCR / MMG 2017
  • Multiple conveyors 750-1000mm wide
  • Idler package delivered in 16 weeks
Nova Nickel Project
Shark Bay Salt Expansion and Refurbishment Project
Onslow Salt Expansion and Refurbishment Project
Nova Nickel Project
Nova Nickel Project – GRES 2015
  • Multiple conveyors 750-1000mm wide.
  • Idler package delivered in 14 weeks.


Shark Bay Salt Expansion and Refurbishment Project
Shark Bay Salt Expansion and Refurbishment Project
  • Multiple conveyors 800, 900,1000mm wide
  • Idler package delivered in 15 weeks
Onslow Salt Expansion and Refurbishment Project
Onslow Salt Expansion and Refurbishment Project
  • Multiple conveyors 800-1500mm wide.
  • Idler package delivered in 14 weeks.