August Production Update - Looking forward to the challenging months ahead

Tuesday, September 05, 2017

37 regular jobs and in excess of 1000 shafts ready for the day shift assembly lines.


48 x 152Ø 945F 6308 Yeloroll plus some other small quantity orders ready for pressing.


The steel tube stock yard is full ready to start phase 2 of Panama. Two containers of steel will be used in the factory a day manufacturing our regular and project work over the next 3 months.